NOTICE: You have clicked on a link that leaves the New Braunfels Utilities website and you will be redirected to a third-party website. New Braunfels Utilities provides this link for your convenience for purely informational purposes and makes no representations nor has any supervision or control over the quality, content, reliability, or security of the third-party website. By clicking on this link, you do so entirely at your own risk and subject to the terms and conditions of use for the third-party website.

Cancel Accept

FOR IMMEDIATE RELEASE
Contact: Melissa Krause
Chief Communications and Strategy Officer
830.629.8440 | mkrause@nbutexas.org

(New Braunfels, TX – July 30, 2021) – New Braunfels Utilities will install a 24-inch water line along Independence Drive between State Highway-46 and Loop 337 as part of its Oakbrook Elevated Storage Tank Capital Improvement Project. The public should expect road and lane closures along Independence Drive through September 3, 2021.

The project will be completed in three phases with road and lane closures scheduled until the work is completed.

Phase 1. Start: Tuesday, July 27, 2021 | End: Friday, September 3, 2021
Daily Closure Times: 24 hour-a-day closure – Consists of lane closure to northwest half of Independence Drive for approximately 400 feet in length, starting at Intersection with State Highway-46.

Phase 2a. Start: Tentatively Monday, August 9, 2021 | End: Tentatively Friday, August 13, 2021
Daily Closure Times: 24 hour-a-day closure – Consists of full road closure, in one location, approximately 400 feet from the Intersection with State Highway-46.

Phase 2b. Start: Tentatively Monday, August 30, 2021 | End: Tentatively Friday, September 3, 2021
Daily Closure Times: 24 hour-a-day closure – Consists of full road closure, in one location, approximately 700 feet from the Intersection with State Highway-46.

Phase 3. Start: Tentatively Monday, August 16, 2021 | End: Tentatively Friday, August 27, 2021
Daily Closure Times: 24 hour-a-day closure – Consists of behind the curb work approximately 400 feet to 700 feet from the Intersection with State Highway-46.

New Braunfels Utilities provides up-to-date traffic impacts for Capital Improvement Projects such as this one on nbutexas.com/current-construction-impacts-and-road-closures, and on its Facebook and Twitter social media channels.

All work is expected to be completed as scheduled, weather permitting.
Contact Desirae Medellin at 830.608.8971, or dmedellin@nbutexas.com with any questions regarding the Project.

###